BusinessPhoto: Mercom IndiaTelangana Regulator Rules Grid Support Charges Must Be Capacity-Based
The Telangana Electricity Regulatory Commission (TGERC) has ruled that grid support charges for co-located captive power projects must be based on installed capacity. Charges will exclude capacity supplied to third parties via open access and capacity committed under power purchase agreements with distribution licensees. This ensures chargeable capacity is calculated after these deductions.
Mercom India·