TechnologyPhoto: Zee News HindiIndia's First Bullet Train Hits Milestone in Vadodara on Delhi-Mumbai Route
In Vadodara, Gujarat, the Mumbai-Ahmedabad High-Speed Rail project achieved a key milestone by installing all 14 portal beams over the Delhi-Mumbai Rajdhani track. This 8.3 km section crosses five railway lines. Engineers used cast-in-situ methods due to space constraints. With beams in place, 40-meter composite girders are now being laid, advancing the elevated viaduct construction for India's first bullet train corridor.
Zee News Hindi··Vadodara