BusinessPhoto: Mercom IndiaCERC Extends SCOD, Waives Transmission Charges for Gujarat Hybrid Project
The Central Electricity Regulatory Commission (CERC) has extended the scheduled commercial operation date (SCOD) for a 250 MW wind-solar hybrid project in Gujarat to June 30, 2026. This extension allows the developer to claim a full waiver of interstate transmission system (ISTS) charges for the capacity commissioned by that date, benefiting the 175 MW hybrid project.
Mercom India··Gujarat